A volume for pricing and planning
Excavators are paid by the hour, by the load or by the cubic meter, and most estimates begin with the volume of the hole. This page gives that number from three measurements and offers a second figure with a percentage on top. Use it for pits, trenches and tank holes where the sides are close to vertical or where you can use average dimensions. It differs from a general take-off in that it asks for nothing else: no soil type, no equipment, no price. Those are separate questions, and the cubic-meter figure is the common input to all of them.
Reading the inputs
Length and width are the plan dimensions of the hole, and depth is the vertical distance to the bottom. The defaults are 10 m, 4 m and 0.1 m with a 10 percent allowance, producing 4 m³ and 4.4 m³. For a real pit, replace each value. If you measure in feet, convert first: one foot is exactly 0.3048 m. A pit 12 ft by 8 ft by 5 ft deep, for example, is 3.6576 m by 2.4384 m by 1.524 m, which is 13.592 m³, equal to 17.78 yd³. Doing the conversion before you enter the numbers avoids unit mismatches. The same pit is 480 ft³, and dividing by 27 gives the 17.78 yd³ directly, a handy cross-check when a US contractor quotes in yards. If the two methods disagree, one of the dimensions was mistyped, and finding it before the order is cheap. Write the unit next to every number in your notes.
Example: a pipe trench
A water or drain trench 40 m long, 0.8 m wide and 1.2 m deep has a volume of 38.4 m³. If you leave the allowance at 0, the page returns the same number for both outputs. Trench width depends on the pipe diameter and the room needed to lay and joint the pipe, and designers usually set a minimum. Deeper trenches may need sloping or support, and a 1.2 m depth already approaches the 1.5 m level at which many safety rules start to require protection. Check the rules that apply in your area. A trench also needs a safe way in and out for workers, spoil kept back from the edge so its weight does not load the wall, and a plan for rain, since water flows into the lowest point. Pipe bedding and the backfill above it are quantities of their own: the bedding layer under a pipe is another thin rectangle, and the trench volume minus the pipe and bedding gives the backfill.
Example: sloped sides and the mid-section trick
A pit with a 10 m by 6 m bottom, a depth of 2 m and side slopes of 1 horizontal to 1 vertical has a top of 14 m by 10 m. The exact volume is 194.67 m³. Entering the bottom dimensions gives only 120 m³, and the top dimensions give 280 m³. A good approximation is to use the dimensions at mid-depth, 12 m by 8 m, which gives 192 m³, within about 1.4 percent of the exact value. That trick is why the page works for sloped pits as long as you are careful about which dimensions you enter.
Working space and over-digging
The hole for a footing, a tank or a foundation is bigger than the object it will hold, because workers need room to build forms, place the object and backfill. Common working space is added on each side of the object, and the amount is set by the contractor or the rules of the job. A 3 m by 2 m tank in a pit 1 m wider on each side calls for a 5 m by 4 m hole at plan level. Over-digging beyond the plan also happens, and the allowance field is a quick way to capture it.
Bank, loose and compacted quantities
The measured volume is the amount of ground removed. When the soil is loaded onto trucks, the loose volume is larger, and when it is placed back and compacted, the volume may be smaller than the original or about the same, depending on how much compaction effort is used. Contracts need to state which volume they use for payment. When you compare quotes, ask each bidder whether they price by bank, loose or compacted cubic meter. The same job can look cheaper or more expensive just because of the volume basis.
Water, rock and surprises
Groundwater adds cost through pumping and handling, and rock can slow digging by a large factor. Neither changes the geometry of the hole, but both change the price per cubic meter. A test pit or a geotechnical report reduces the risk of surprises. Buried obstructions such as old foundations, tanks and utilities are more common than people expect on older sites. Build a contingency into your budget, and keep records of the actual volume removed so that you can reconcile it with the invoice.
Converting units
One cubic meter equals 1.307951 cubic yards and 35.3147 cubic feet. A hole of 38.4 m³ is therefore about 50.2 yd³. Trucks in many markets are rated in cubic yards or cubic meters of body capacity, and the loose volume determines how many loads you need. Divide the volume with allowance by the truck capacity and round up, then compare with what the hauler quotes. Keep one unit through the whole calculation, and convert only at the end. For a rough truck count, take the 38.4 m³ trench with a 20 percent allowance, which is 46.08 m³ loose. A truck body of 8 m³ would need six loads, since 46.08 / 8 is 5.76. Real trucks are rarely filled to the brim and the hauler rounds trips, so ask for a quote on the number of loads, not only the cubic meters. A site that sends spoil to several destinations may price each haul separately.
Why real excavations have sloped sides
The page assumes a rectangular excavation of uniform depth. It does not infer compaction, moisture, density or supplier yield, and it does not size a structural member or design shoring. Sloped sides, steps in the bottom and curved outlines have to be handled with averages or split into pieces. Confirm quantities with a surveyor, contractor or engineer for any job that is paid by the measured volume.