Bank volume and loose volume

Soil in the ground has a volume, and soil in a truck has a larger one. When ground is dug up, the particles lose their packed arrangement and trap air, so the same mass takes up more space. Earthmoving references call the in-ground figure the bank volume and the dug-up figure the loose volume. The excavation calculator gives you the bank volume from the dimensions and a second figure with an allowance percentage, which you can use as a stand-in for that expansion. That makes it useful for planning haul trips and disposal. It does not predict the expansion itself, so you pick the percentage.

The formula and defaults

Measured volume = length × width × depth, and the volume with allowance = measured volume × (1 + allowance / 100). With the opening values of 10 m, 4 m, 0.1 m and 10 percent, the page shows 4 m³ and 4.4 m³. The dimensions describe a shallow rectangle, so change them to your hole. All three are in meters, and the depth is the vertical distance from the existing surface to the planned bottom. Because the allowance is applied to the volume and not to the dimensions, the measured figure always matches what you would pay a surveyor to confirm, and the second figure answers a separate question about hauling.

Example: a basement dig

A basement excavation 10 m by 8 m and 2.5 m deep has a measured volume of 200 m³. If you assume the soil swells by 25 percent when dug, the allowance result is 250 m³. A truck that hauls 10 m³ loose would need 25 loads, and a smaller truck needs more. These truck numbers are illustrative. The actual swell depends on the soil, which a geotechnical report or the contractor can estimate. Sand and gravel tend to swell less, and heavy clay more, and the figure can differ for rock. Use the allowance that the project documents or your contractor specify. If you want a range, run the page twice with a low and a high percentage, for instance 15 and 35 percent. The basement then gives 230 m³ and 270 m³ of loose soil, and the spread tells you how sensitive the haul plan is to that single assumption. A wide spread is a reason to ask for soil data before you commit to a trucking schedule.

Example: a swimming pool shell

A rectangular pool excavation of 8 m by 4 m and 1.5 m deep is 48 m³ measured. With a 20 percent allowance for loosened soil, the result is 57.6 m³. Pool excavations usually go beyond the finished shell, because the walls need working room for formwork, plumbing and backfill. Entering the planned excavation size, not the water surface size, gives the quantity that must be removed. A pool with a deep end has a sloping bottom, and an average depth is a fair approximation if the slope is uniform. A more complicated shell needs to be broken into sections. Suppose the shallow half of the pool is 1.0 m deep and the deep half is 2.0 m, each half 4 m by 4 m. The shallow half is 16 m³ and the deep half is 32 m³, a total of 48 m³, the same as the uniform 1.5 m average above. Splitting by depth keeps the arithmetic honest when the floor has a distinct step, and you can add an allowance to each part separately if the soil differs.

Where the soil goes

Excavated soil can be reused on site, stockpiled for backfill, hauled away or sold. Each choice has costs. A stockpile needs room and cover to control erosion, and soil kept on site occupies its loose volume until it is compacted back in. Hauling charges depend on distance, truck size and disposal fees at the receiving site, and some soils need testing before disposal. The loose volume is the number that matters for trucks and stockpiles, while the bank volume is the number that matters for the hole. Keeping the two figures side by side avoids confusion.

Safety and utilities before you dig

Calling before you dig is the first step on any excavation. In the United States, 811 connects you to the local one-call center that notifies utility owners so they can mark buried lines. Other countries have similar services. In the United States, OSHA excavation rules in 29 CFR 1926 Subpart P require protective systems such as sloping, shoring or shielding for excavations 5 feet (1.5 m) deep or more, unless the excavation is in stable rock. This page covers volume only and gives no safety design, and the competent person on the site and the local rules decide what protection is needed.

Side slopes and over-excavation

A hole with vertical sides is rare in soil. To keep the walls from collapsing, excavators slope them back, so the top of the hole is larger than the bottom. This page assumes a rectangular prism with uniform dimensions. For a sloped excavation, estimate the volume from the average of the top and bottom dimensions at mid-depth, or split the hole into layers. Over-excavation, where the hole ends up bigger than planned for working space or because of soft soil, adds volume as well. Add an allowance to the quantity if the contract pays by the cubic meter removed. Remember too that the sloped walls move the hole boundary outward at the top, which can run into a property line, a fence or a neighbor's retaining wall. Check the setback before you plan a slope, because a steep, shored wall needs less ground than a gentle slope but costs more to build, and the choice shifts the volume you enter.

Keeping records and comparing with survey data

On larger jobs, excavation volumes are checked against surveys of the ground before and after digging. Differences between the planned and surveyed volumes come from over-digging, ground that differs from the drawings, and the accuracy of the original survey. If you are the one paying for the excavation, ask how the quantity will be measured and what units appear on the invoice. Cubic meters are standard in most countries, and cubic yards are used in the United States, where 1 yd³ equals 0.764555 m³. The 200 m³ basement above is about 261.6 yd³.

Slopes and shoring an excavation volume omits

The result is a rectangular volume with a percentage added. It does not infer compaction, moisture, density or supplier yield, and it does not size a structural member or design a shoring system. Real excavations have sloped sides, uneven bottoms and variable depth, so measure carefully and use averages. Confirm quantities with your contractor or engineer, and use the figures here for planning and quick checks, not as a substitute for a survey or a site-specific design.