When a trench is filled with concrete
Concrete goes into a trench in a few common situations. A strip footing carries a wall, and a trench-fill foundation uses concrete poured almost to the ground surface. A thrust block or an encased duct bank also relies on a trench full of concrete. This page handles the shared geometry of all of them: a long rectangle of uniform width and depth. Enter the trench length along its centerline, its width, its depth and an allowance percentage. The page returns the volume and the volume with allowance. It does not choose the footing size, which comes from drawings or code.
Trench concrete from length, width and depth
The measured volume is length × width × depth, and the volume with allowance is that result × (1 + waste / 100). The input defaults are 10 m, 4 m, 0.1 m and 10 percent, producing 4 m³ and 4.4 m³. A real trench is narrower and deeper than that, so change all four values. Width and depth are the two small dimensions of a trench, and mixing them up changes nothing in the product, but typing a width in centimeters or a depth in inches changes it enormously. Keep every length in meters. A 600 mm trench is 0.6 and a 300 mm depth is 0.3.
Example: a strip footing for a small building
Suppose a building measures 8 m by 6 m and the footing runs along the centerline of the wall. The centerline perimeter is 2 × (8 + 6) = 28 m. With a footing 0.5 m wide and 0.25 m thick, the page returns 3.5 m³. A 10 percent allowance brings that to 3.85 m³. Using the centerline length means the corners are counted once, which is why the length is measured there rather than along the outside edge. Measuring the outside perimeter would count each corner area twice. If the footing steps down with a sloping site, calculate each level separately.
Example: a utility trench encased in concrete
A 15 m trench that is 0.45 m wide and filled to a depth of 0.2 m holds 1.35 m³, and a 5 percent allowance raises that to 1.4175 m³. This kind of job is more complicated than the arithmetic suggests, because the conduit or pipe occupies space inside the trench and the concrete only fills around it. If the pipe is large, subtract its volume, which for a round pipe is pi × radius² × length. Utility owners often specify the concrete strength, cover and reinforcement for encasement, so use their requirements for the design and this page only for the quantity.
Trench walls and the extra volume you did not plan
A trench dug with a backhoe has rough sides, and when concrete is poured against soil without forms, the final width follows the excavation rather than the plan. A 0.5 m planned trench that comes out 0.55 m wide holds 10 percent more concrete. Collapsing walls, loose soil falling in and over-excavation at corners all add volume. Because of this, trench pours are among the cases where a generous allowance is justified. Compare the estimated volume with the amount actually placed on each job, and use the difference to set the percentage for the next one. Trench forms or a plastic liner on the sides reduce the overbreak, and a trench cut with a narrow bucket to the exact width gives a result much closer to the drawing. Record the planned and placed volumes for each job so the allowance you choose rests on your own site results and not on a guess.
Choosing between a trench and a formed footing
A trench filled with concrete is quick to build, because the soil acts as the form, and it works where the ground stands up well. In loose or sandy soil, or where the footing must have a precise top edge, builders place forms instead and the concrete volume follows the forms. The volume formula is the same either way, but the allowance changes. Ask your designer whether the footing may be placed against undisturbed soil, because some designs require formwork or a minimum cover to the reinforcement. The answer decides how you measure the width and how much extra you carry. Reinforcing bars set in the trench displace only a tiny fraction of the concrete, so they are normally left to the allowance, while large embedded items such as precast pieces should be deducted. Bar placement, cover and lap lengths come from the plans, not from this page.
Depth, frost and groundwater
The depth of a footing trench is often set by the frost depth in your region, the bearing soil level, or the building code. This page uses the depth you give it without checking any of those. If a trench holds water, concrete placed into it may need to be placed differently, and pumping or dewatering becomes part of the job. Standing water does not change the geometric volume but it changes how you pour and finish. The quantity is a starting point, and the method of placement and curing belongs in the specification from your engineer or inspector.
Stepped footings and sloping sites
On a sloping lot, a footing trench is often stepped so that each length sits on firm soil at a consistent depth below grade. Each step is a short run at one depth, and the vertical overlap where two levels meet is usually at least as thick as the footing itself. Treat every level as its own rectangle: measure its centerline length, its width and its depth, and add the volumes. Suppose three levels run 9 m, 11 m and 8 m, all 0.5 m wide and 0.3 m deep. That is 28 m of footing in total, or 4.2 m³ before any allowance, a figure the page returns if you enter 28 as the length. Draw the steps on paper first so that no length is missed or counted twice, and have the layout approved if an inspector is involved.
Excavation and forming costs beyond concrete
The result is the volume of concrete only. It does not include excavation spoil, forms, reinforcement, formwork ties, compaction of the trench bottom or backfilling. Digging the trench produces a larger volume of loose soil than the trench holds, and that is a separate quantity. The calculator does not infer compaction, moisture, density or supplier yield, and it does not size a structural member. Check dimensions, strength class and inspection requirements with your engineer, building department or utility, and compare the volume with allowance with the supplier's quote.