Reading the three fields for a wall
The calculator labels its inputs length, width and depth, which suits slabs. For a wall, map them to what you can measure. Length is how far the wall runs. Width is the wall height, and depth is the wall thickness. Because the formula is a plain product, the order does not change the answer, but you must keep each number in meters and make sure the thickness is the smallest of the three. A basement wall 11 m long, 2.4 m high and 0.2 m thick holds 11 × 2.4 × 0.2 = 5.28 cubic meters. With a 5 percent allowance, the order figure becomes 5.544. Each wall segment is handled by one run of the calculator.
Concrete for a 10 meter basement wall run
The defaults of 10 m, 4 m and 0.1 m with a 10 percent allowance give 4 cubic meters and 4.4 cubic meters. As a wall, that would be a 10 m run 4 m high and only 100 mm thick, which is thinner than a typical foundation wall, so the defaults are a demonstration of the arithmetic, not a specification. The point is to show the relationship: halving the thickness halves the volume, and doubling the height doubles it. Replace the defaults with your own dimensions before you use the result for anything. The required thickness and strength of a basement wall belong to your structural drawings.
Handling a whole rectangular basement
A basement has four walls, and the corners are where mistakes happen. If you measure each wall along the outside face, the corner blocks are counted twice. A neat method is to take two opposite walls at full outside length and the other two between them. For a basement 11 m by 8 m outside with 0.2 m walls 2.4 m high, run the two 11 m walls at 5.28 cubic meters each. The other two walls are 8 − 2 × 0.2 = 7.6 m long between the first pair, giving 7.6 × 2.4 × 0.2 = 3.648 cubic meters each. The total of 17.856 cubic meters counts every corner once.
Deducting openings
The page does not subtract windows, doors or service penetrations. If an opening is large enough to matter, calculate its volume with the same formula and subtract it from the wall. A window opening 1.2 m wide and 0.6 m high in a 0.2 m wall removes 1.2 × 0.6 × 0.2 = 0.144 cubic meters. Small penetrations for pipes and cables remove almost no volume, and most builders ignore them. A bulkhead door for access to a basement is larger and worth deducting. Be consistent: if you deduct openings, say so in your notes, so that you do not also subtract them again from the allowance percentage.
Footings and the wall base
The footing under a basement wall is a separate pour with its own dimensions, usually wider than the wall and cast first. Do not add its depth to the wall height unless you are pouring them together in one operation, and in that case their widths differ, so a single rectangle does not describe them. Calculate the footing as another rectangle, using its length, its width and its depth, and add the volumes. The same applies to a wall that steps in thickness partway up, such as a brick ledge. Treat each part as its own rectangle and keep the sections in a short list.
Form overfill and spillage in wall pours
Concrete in a wall is placed in a form, and the volume of the form is the true quantity, but real forms flex, and surfaces are not perfectly plumb. Pumping loses some concrete in the hose and hopper, and any left in the truck is a cost that you pay for. Many people therefore add a margin to the calculated volume. The page applies whatever percentage you enter once, to the total. The right figure depends on how accurate your formwork is, how the concrete is placed and how the supplier charges for returns, so there is no single value to recommend. Ask your concrete supplier about their practice.
Ordering concrete
Ready-mixed concrete is ordered by volume, in cubic meters in most of the world and cubic yards in the United States. One cubic meter is about 1.30795 cubic yards, so the 5.544 cubic meters above would be about 7.25 cubic yards. Suppliers deliver in truckloads and may charge extra for small loads or waiting time. Tell the supplier the intended use, the strength class you need as specified by the designer, and the slump or workability required. Concrete mixes for walls and slabs are not interchangeable, and the page does not choose one. The concrete cost calculator on this site turns an ordered volume and a unit price into a total.
A retaining wall in sections
Basement walls sometimes change height along their length, for example where the ground slopes or a stair well steps down. The page cannot describe a sloping top edge directly, but you can approximate it with steps. A wall 12 m long that is 2.4 m high for the first 8 m and 1.8 m high for the last 4 m is two rectangles at 0.2 m thickness: 8 × 2.4 × 0.2 = 3.84 cubic meters and 4 × 1.8 × 0.2 = 1.44 cubic meters, a total of 5.28. A genuinely sloping top is a trapezoid, whose area is the average of the two end heights times the length, so averaging the heights gives the same volume as the exact shape.
Weight and handling
Normal-weight concrete is commonly taken to weigh around 2,400 kg per cubic meter, so the 5.544 cubic meters above would weigh roughly 13,300 kg when placed. Forms must be designed to resist the pressure of fresh concrete, which acts like a heavy liquid and increases with the height of a pour. This is a matter for the formwork designer or supplier. The calculator estimates quantity only. Wall height per pour, placing rate and the use of vibration all affect formwork loads, and none of them are inputs here.
What the page cannot do
The result is a geometric volume from dimensions you supply. Soil pressure, waterproofing, drainage, reinforcement and the structural adequacy of the wall are outside the calculation and need their own assessment by a qualified person using local codes. The page requires finite numbers and cannot return a result for blank or invalid input. Keep your intermediate figures at full precision while you check a calculation, and round only the order you pass to the supplier.