A cylinder in the ground

A concrete pier is a round column of concrete, usually poured into a bored hole or a tube to carry a post, a deck beam or a light structure. Its volume is that of a cylinder, which is pi times the radius squared times the depth. The page asks for the internal diameter of the hole or form and the depth of the fill, both in meters, and returns cubic meters. A second figure includes an allowance for irregular excavation and spillage. The calculator does not determine the pier size, the soil bearing or the structural adequacy, which are matters for the design.

Cylinder volume for a 2 meter pier

Volume = pi × (diameter / 2)² × depth. The defaults of a 2 m diameter, 1 m depth and 0 percent allowance return pi, 3.141592653589793 cubic meters. Such a pier is far larger than any normal one and the example works as a check: a radius of 1 and a depth of 1 give pi. Because the radius is squared, the diameter has a strong effect. Doubling the diameter quadruples the volume, and doubling the depth only doubles it. That is why a small error in a hole diameter, especially a large auger, changes the concrete quantity more than you might expect.

A deck footing and a larger pier

A deck footing with a 0.3 m diameter and a depth of 1.2 m holds pi × 0.15² × 1.2 = 0.08482 cubic meters. With a 10 percent allowance, the order is 0.09331 cubic meters, about 93 liters. A larger pier, 0.45 m in diameter and 1.5 m deep, holds 0.23856 cubic meters, and a 0.6 m diameter pier at 0.9 m deep holds 0.25447 cubic meters. The 0.6 m pier is shallower than the 0.45 m pier, yet it holds more concrete, because its cross-sectional area is almost twice as large. That comparison shows why diameter matters more than depth.

Many piers, one order

A deck or porch often needs a dozen or more piers. Calculate one, multiply by the count and then apply the allowance once. Twelve of the 0.3 m by 1.2 m piers need 12 × 0.08482 = 1.01788 cubic meters before the allowance. Each pier is a small volume, so a bagged mix may be practical for a few of them, while a dozen piers might justify a ready-mix delivery. If the piers differ in depth, group them by depth and add the group volumes. Keep unrounded figures until the end to avoid accumulated rounding differences.

The excavation is not a perfect cylinder

A bored hole usually has a rough wall, and a hole dug by hand is more irregular still. The actual concrete needed is greater than the ideal cylinder, because the hole is often wider than the auger, and it flares at the top. Using a form tube prevents that flare and gives a more predictable quantity. The page notes that irregular excavation can change the actual quantity, which is the reason the allowance exists. Measure the hole at the top, middle and bottom, and use an average diameter. A larger percentage is reasonable for hand-dug holes in loose soil.

Depth, frost and soil

The depth of a pier is not the page choice. It is set by the structure, the soil and the local frost depth, since footings in cold climates must usually extend below the depth to which the ground freezes so that frost heave does not lift them. Local building authorities publish those depths. The calculator uses the depth that you enter as the fill depth and assumes that the pier is poured full from the bottom of the hole to the top of the fill. Foundation sizing, soil bearing and structural adequacy are outside this cylinder estimate.

Using a form tube

A cardboard or plastic form tube set into the hole keeps the concrete shaft round and stops soil from falling in. The calculator asks for the internal diameter, which for a tube is the inside of the tube, not the outside and not the size of the hole around it. A tube sold as 12 inches has an internal diameter near 0.3048 m, from 1 inch = 25.4 mm. Where the hole is wider than the tube, the gap is normally backfilled with soil, so the concrete only fills the tube. Check the tube length against the depth you enter, and remember that the part standing above ground to hold a post bracket still needs concrete.

Belled and tapered piers

Some piers are belled at the bottom, which means the hole is enlarged near its base to spread the load over more soil. A bell is not a cylinder, and the page does not represent it. You can estimate the bell as a second cylinder of larger diameter and short height, calculate it separately and add it to the shaft. A tapered form can be approximated by an average diameter. If the shape matters for structural reasons, the designer should give the volumes or the dimensions that the form must have.

Bagged mix for a few piers

For one to four small piers, bagged concrete mix is often practical. The label states the yield of each bag, for example about 0.6 cubic feet for an 80 lb bag in the United States, which is roughly 0.017 cubic meters. The 0.09331 cubic meter deck footing above would need about 5.5 such bags, so you would buy 6. Read the label of the product you actually buy, because yields differ by brand and by bag size. Mixed on site, the water ratio on the bag affects strength, so measure it. Dry mix poured around a post and wetted in place is a method some manufacturers describe, but follow the instructions on the product.

Ordering, placing and curing

Pier holes should be cleaned of loose soil before the pour, and concrete should be placed so that it does not segregate on its way down. A tube or chute helps. If the hole is wet, the water must be dealt with before the concrete goes in. Anchor bolts or post brackets are set while the concrete is wet, so measure and mark their positions first. Allow for the curing time that the designer or the product maker states before you load the piers. The calculator reports the quantity only, and the rest comes from your plans.

Bells, footings and rebar around a pier

The result is a cylinder of the diameter and depth you enter, plus a percentage. It does not size the pier, the reinforcement or the footing, and it cannot account for irregular holes or a belled base. Treat it as the starting point for an order, confirm the quantity with your supplier and rely on the structural design for sizes. The calculator needs finite numbers to give a result.