ARITHMETIC WORKSHEETS

Checking why average workload does not establish a feasible finish time

Total work divided by the number of workers gives the fastest finish time that could ever be possible. Whole tasks often make the real minimum longer.

The question behind the division

Suppose a job consists of several tasks with known durations and a fixed number of identical workers. The first thing most people do is add the durations and divide by the workers. That quotient is useful, but it answers a narrower question than the one being asked. It says how long the job would take if work could be poured evenly into every worker like water. Real tasks are lumps. This page uses a small example to show why the quotient is a floor under the finish time and not a schedule, and how to find out when the floor can actually be reached.

Total work and the lower bound

The example has three tasks of duration 6 each, so the total work is 3 × 6 = 18 time units. With two identical workers, the average share is 18 / 2 = 9. No schedule can finish before time 9, because two workers cannot complete 18 units of work in less than 9 units of time, even with no idle moments. That is why the quotient counts as a lower bound. The basic calculator handles both steps in the first two cases below. The division does not say a schedule with a finish time of 9 exists, only that nothing faster can exist under this model.

Why 9 cannot be reached here

Reaching 9 would require each worker to finish exactly at time 9, so each would need tasks adding to 9. The only task length is 6, and the multiples of 6 are 0, 6, 12 and so on. No combination of whole tasks equals 9. Three tasks on two workers means someone gets two tasks, taking 2 × 6 = 12 time units, while the other worker takes 6 and then waits. The finish time of the whole job is the later of the two, which is 12. Another way to see it: a split of 18 into two whole-task piles can only be 6 and 12 or 0 and 18, and the smaller maximum is 12.

The gap between bound and schedule

Here the gap is 12 - 9 = 3 time units, a third more than the bound. It comes entirely from indivisibility. If the third task could be cut into halves, with 3 units handled by each worker after they finish their first tasks, both workers would finish at 9. Splitting a task is called preemption in scheduling theory, and it requires that partial work can be moved or resumed without loss. Many real jobs allow it only at a cost, and some do not allow it at all, such as a machine run, a surgery or a single code compile that cannot be paused and handed over.

Bounds that tighten the estimate

Two simple bounds are used together. The average bound is total work divided by workers. The longest-task bound says the finish time is at least as long as the longest single task, since one task cannot be shared. The true minimum is at least the larger of the two. In this example the longest task is 6, below 9, so the average bound is the stronger of the two, yet it is still not achievable. Another useful observation: with n tasks of equal length on m workers, the finish time is the task length times the ceiling of n / m, here 6 × ceil(3 / 2) = 6 × 2 = 12.

A second look with different numbers

Take four tasks of duration 6 on two workers. Total work is 24, the average bound is 12, and the schedule of two tasks per worker finishes at 12 as well, so here the bound is reached. Take five tasks of duration 6 on two workers: total 30, bound 15, but the best finish is 6 × ceil(5 / 2) = 18. The bound is reached only when the tasks happen to divide evenly. As the number of small tasks grows relative to the number of workers, the gap tends to shrink in relative terms, so the average becomes a better guide for large mixed workloads. Even then it remains a floor, never a promise, and a few long tasks can keep the gap wide.

Assumptions built into the example

The example assumes both workers are available from the start and stay available, that every task can run on either worker, and that tasks are independent. If one task must precede another, the chain of dependencies sets another lower bound, the critical path length. If workers differ in skill or speed, the average of durations is no longer meaningful, because a task takes different time on different workers. Changing any of these conditions defines a different problem, and the calculation here would have to be redone for that problem rather than adjusted. A pool of workers who join at different times is one more example, since then the average must be taken over available worker-time and not over a head count.

How to use the bound responsibly

Use the quotient to reject impossible promises. If a team of two is told to finish 18 hours of work in 8 hours, the bound of 9 shows the target cannot be met. Do not use it to promise a date. For a commitment, build an actual assignment of whole tasks to workers and take the latest finish. The page is an arithmetic illustration and gives no staffing advice, and it makes no statement about how real work should be divided. The three calculations in the cases below use whole numbers, so each result is exact. Keep the units consistent as well: durations in minutes for every task, and the same time base for the finish time you compare against a deadline.

Where whole-task scheduling shows up

The same arithmetic appears in many ordinary settings. Three loads of laundry of 60 minutes each cannot be finished in 90 minutes on two machines, although 180 / 2 = 90 suggests they could. Three reviewers handling six-hour reviews of three documents, two movers carrying three equal pallets, two ovens baking three trays: each has a bound that whole units prevent from being reached. Operations researchers study the general version under the name makespan minimization on identical machines, and finding the exact best split of uneven tasks is a hard problem for large cases. For small sets like this one, listing the possible splits by hand is enough.

Reproduce the checks

Total work

Open the Basic calculator and enter:

First number
3
Operation
multiply
Second number
6

Expected output:

Result

18

There are three complete tasks.

Average-work lower bound

Open the Basic calculator and enter:

First number
18
Operation
divide
Second number
2

Expected output:

Result

9

This division permits fractional balancing algebraically.

Two indivisible tasks on one worker

Open the Basic calculator and enter:

First number
2
Operation
multiply
Second number
6

Expected output:

Result

12

At least one worker receives two tasks in this example.

References and implementation scope

The examples describe the behavior of the linked Computandum tools. A successful local check does not establish that another application accepts the same format or applies the same limits.