Dependency schedule calculator

Enter one task per line as id,duration,dependencies. The dependency column uses semicolons, and a task with no dependencies still needs the trailing comma.

No header. Use the same duration unit throughout.

Result

Earliest finish
9
Total task duration
11
Resource model
Unlimited parallel resources
TaskDurationEarliest startEarliest finish
A303
B538
C235
D189

Read the earliest schedule

In the sample, A finishes at 3. B and C then run in parallel and finish at 8 and 5. D waits for both and finishes at 9. Total task duration is 11, while the earliest overall finish is 9.

Respect the resource assumption

The report assumes unlimited parallel resources, zero transfer delay and no calendars. It is a precedence calculation, not a staffing commitment. Enter at most 100 tasks with unique IDs and nonnegative decimal durations. Unknown dependencies and cycles are rejected. IDs contain letters, digits, underscores or hyphens; each line has exactly three comma-separated fields. Decimal arithmetic uses 50 significant digits with each duration at most 10^20.

Work through the reasoning

Checking a simple dependency schedule through its longest path