Dependency schedule calculator
Enter one task per line as id,duration,dependencies. The dependency column uses semicolons, and a task with no dependencies still needs the trailing comma.
Result
- Earliest finish
- 9
- Total task duration
- 11
- Resource model
- Unlimited parallel resources
| Task | Duration | Earliest start | Earliest finish |
|---|---|---|---|
| A | 3 | 0 | 3 |
| B | 5 | 3 | 8 |
| C | 2 | 3 | 5 |
| D | 1 | 8 | 9 |
Read the earliest schedule
In the sample, A finishes at 3. B and C then run in parallel and finish at 8 and 5. D waits for both and finishes at 9. Total task duration is 11, while the earliest overall finish is 9.
Respect the resource assumption
The report assumes unlimited parallel resources, zero transfer delay and no calendars. It is a precedence calculation, not a staffing commitment. Enter at most 100 tasks with unique IDs and nonnegative decimal durations. Unknown dependencies and cycles are rejected. IDs contain letters, digits, underscores or hyphens; each line has exactly three comma-separated fields. Decimal arithmetic uses 50 significant digits with each duration at most 10^20.
Work through the reasoning
Checking a simple dependency schedule through its longest path