Time for a single cutting move

Every machining operation includes moves where the tool advances through material at a programmed feed rate. The time for one such move is the distance divided by the speed, and this page does exactly that for a straight path. It suits a facing pass across a plate, a slot of known length, one pass of a contour along a straight edge or a single drilled hole if you treat the depth as the travel. The answer is the time spent actually feeding the tool through the cut. It is the building block for larger estimates, which add several moves together, and it gives a quick check on whether a program is likely to be fast or slow before you run it on a machine.

Machining time from cut length and feed rate

Time equals length divided by feed: t = L / vf. With L in millimeters and vf in mm/min the result is in minutes. The relation is the straightforward form of distance over speed, and Sandvik Coromant's milling formulas reference uses the same definition of machining time for a straight feed. The feed rate itself comes from tool guidance. In milling it is the table feed, which equals feed per tooth times the number of teeth times the spindle speed, vf = fz × z × n. The page takes the feed rate as given and does not derive it, so enter the value your program or setup actually uses. If the program contains several different feeds, for example a slower plunge and a faster cut, estimate each move separately and add the times, because one average feed hides the effect of the slow sections.

A 100 mm pass at 200 mm per minute

The page opens with a feed travel of 100 mm and a feed rate of 200 mm/min. Dividing gives 0.5 minutes, which is 30 seconds. Doubling the feed rate halves the time, and doubling the length doubles it, so the relationship is easy to scale in your head. The example is a single straight movement with no approach, so it is the cutting time only. A real cycle containing this pass would also include positioning moves and any tool change, and those are outside the figure shown here.

Slot and short-cut times compared

A 240 mm slot cut at 150 mm/min takes 1.6 minutes, or 96 seconds. A short 75 mm cut at 300 mm/min takes 0.25 minutes, or 15 seconds. A long 1,250 mm edge at 400 mm/min takes 3.125 minutes. When a surface needs several passes, multiply by the number of passes: three passes of 240 mm at 150 mm/min total 4.8 minutes. To work out how many passes a pocket needs, divide the total depth by the depth of cut per pass and round up, so 10 mm deep at 2 mm per pass is 5 passes. These small calculations show how quickly total time grows with passes.

Getting the feed rate

In milling, the table feed combines the tool's tooth count, the feed per tooth and the spindle speed. A cutter with 4 teeth at 0.1 mm per tooth turning at 2,000 rpm feeds at 4 × 0.1 × 2,000 = 800 mm/min. On a lathe or a drill the feed is given per revolution, and the feed rate is that value times the rpm. CNC controls may use mm/min or mm/rev, so check which mode your program is in. Feed per tooth comes from the tool manufacturer's catalog for the specific cutter and material. The page offers no recommendation, so any value you enter must be supported by the tool data and your machine's capacity.

Measuring the length of travel

The feed travel is the distance the tool moves while cutting, not the length of the part. For a facing pass it equals the part length plus the tool diameter or the cutter overrun at both ends if the tool starts and finishes outside the material. For a closed pocket or a slot it is the path length of the toolpath. A drill's travel is the hole depth plus the point allowance. A curved path should be entered as its total arc length. Using the nominal part dimension when the tool travels farther understates the time, which is why careful estimates start from the toolpath length shown in the CAM software. A 100 mm part faced with a 50 mm cutter that clears the material by 10 mm at each end, for instance, travels 100 + 50 + 20 = 170 mm in practice, and at 200 mm/min that is 0.85 minutes, well above the 0.5 minutes of the bare part length.

What the time does not include

The result excludes acceleration and deceleration, tool changes, approach, retraction and dwell, as the page assumptions state. On small parts with short moves, those items can take more time than the cutting itself, because a machine rarely reaches the programmed feed over a few millimeters. Rapid positioning moves between cuts, probing, workpiece loading and coolant changes are also outside the figure. For scheduling, add a separate allowance for them, or use the cycle time reported by the CAM or control simulation, which models acceleration and rapids. This page gives the cutting travel time, a lower bound on the actual cycle.

Turning minutes into cost

Machining time becomes money when multiplied by a machine rate. If a machine costs 60 per hour to run, then 4.8 minutes of cutting is 4.8 / 60 × 60 = 4.80 in machine cost for those passes. The same time multiplied by the number of parts in a batch gives the total spindle time to quote. Shops usually add setup time, tool wear and inspection on top. Using the cutting time alone underprices a job, but it correctly shows which operations dominate. If the longest pass consumes half the total, reducing its length or raising its feed within safe limits has the biggest effect on cost.

Feed rates and tool checks left to the machinist

This is a scalar educational model that returns a finite number from two inputs. It does not recommend a feed rate, check tool or machine limits, or model material behavior and safety. A feed that gives a short time may be unsafe or unachievable for the tool, so confirm feeds against the manufacturer's data and the machine manual. The page is suited to quick estimates, comparing alternatives and checking a CAM report, and it should be read as the minimum cutting time, never as a promise of how long the machine will actually take.