Gravel is bought by the layer

Paths, driveways, drainage trenches and the base under a patio all use gravel laid to a planned depth over a known area. The supplier quotes cubic meters or tonnes, so the first step is to convert the layer into a volume. This page multiplies the area you cover by the depth of the layer and gives cubic meters. It treats the surface as a rectangle with a uniform layer, which fits straight paths and rectangular beds well. It does not select a depth for your application. A footpath, a parking area and a drainage layer have different needs, and the right depth comes from the project design or the local guidance for that use.

Reading the formula

The measured volume equals length times width times depth, with all three in meters. The order volume equals that figure times one plus the allowance divided by 100. If length is 10 m, width is 4 m and the depth is 0.1 m, the volume is 4 m³. A ten percent allowance gives 4.4 m³, the default result. Depth is the input that most often goes wrong. Gravel layers are often described in millimeters or centimeters, so convert before typing: 150 mm is 0.15 m, and 5 cm is 0.05 m. The result shows six decimals, though practical orders round to a tenth or a half of a cubic meter.

A driveway example

A driveway strip 15 m long and 3 m wide that receives a 0.15 m layer needs 15 × 3 × 0.15 = 6.75 m³ of gravel. With a 10 percent allowance, the order volume is 7.425 m³. A supplier might round that to 7.5 m³ for loading. The allowance is there because spreading is never perfectly level, some material sinks into soft ground and a few buckets disappear at the edges. If the base is well compacted and edged, a smaller percentage may be enough. If it is soft and uneven, you may want more. Neither choice is built into the calculator, which uses only the number you enter.

A thin path layer

Thin layers add up quickly over long distances. A garden path 12 m long and 0.9 m wide, covered to a depth of 0.05 m, needs 12 × 0.9 × 0.05 = 0.54 m³. With a 10 percent allowance the order volume is 0.594 m³. That is small enough that bags may be more practical than a bulk delivery. For example, a 25 kg bag holds an amount that depends on the density of the stone, so check the bag label for its volume or use the Gravel Weight Calculator on this site to relate kilograms and cubic meters. A very thin layer is also the least forgiving, since a few millimeters of unevenness is a large share of the depth.

Separate layers for separate depths

Many projects use more than one layer, such as a coarse sub-base topped with a finer surface course. Each layer has its own depth and sometimes its own stone size, so calculate each one separately and add the volumes only if the supplier sells them as one product. For a base under pavers, the bedding layer is thin and the sub-base is thicker. Calculating them together with an average depth hides the fact that they are different materials with different prices. If an area is not a rectangle, divide it into rectangles, add the net areas, and use one depth for each layer.

Compaction and what the volume means

The measured volume is the space the finished layer occupies. Loose gravel is delivered with air between the stones, and compaction reduces the volume of a layer that is rolled or tamped. The calculator does not infer compaction, moisture, density or supplier yield. If the project calls for a compacted layer of known thickness, ask the supplier whether the quoted volume refers to loose or compacted material, and increase the allowance accordingly. Suppliers who sell by weight may quote a yield in square meters per tonne at a given depth, and that figure comes from their own material, not from this page.

From volume to weight and cost

Once you know the order volume, two more steps are common. To find the weight, multiply the volume by the supplier bulk density in kilograms per cubic meter, which the Gravel Weight Calculator does. To find the price, multiply the volume by the quoted price per cubic meter and add delivery, which the Gravel Cost Calculator does. Keeping the three steps separate keeps each number checkable. A truck may have a payload limit, so converting to weight also tells you whether the order has to be split across loads. The weight is only as good as the density you use for the actual stone.

Edging, geotextile and the other materials in a gravel job

Gravel is rarely the only item on the order. Edging holds the layer in place, a geotextile membrane keeps it from mixing with the soil below, and a sand or fine layer may sit under pavers. The area you enter for the gravel should be the surface that receives it, which is usually the same as the area of the membrane. Check whether the membrane overlaps at the seams, because that adds to its area and not to the gravel. When the layer meets a raised edge, the depth may be set by the height of that edge, so measure it before you decide on the number you type. Treat each material as its own calculation and keep the quantities in separate lines of your shopping list, so a change to the gravel depth does not silently change the membrane order.

Checking the setup before you order

Before ordering, measure the area twice and check units. A common slip is typing a depth in centimeters, which inflates the result a hundredfold. Another is using the outside dimensions of an edging that the gravel will not fill. Compare the result with a rough mental check: one cubic meter of gravel spread 0.1 m deep covers 10 m². The default fits that rule, since 4 m³ at that depth covers 40 m². The calculator cannot see the site. It does not account for slopes, steps, drainage falls or soft spots, so adjust the depth or the allowance if the ground is not flat.